The port engine for the CCGC Sambro is due for a 10,000 hour overhaul. This engine must be overhauled in situ. The vessel will be tied up alongside at Bedford Institute of Oceanography.
1. Contractor shall prepare the engine for overhaul. This shall include but is not limited to: draining fluids, disconnecting pipe work, and disconnecting electrical connections.
2. Contractor shall quote on providing all parts and labour for the engine overhaul:
Parts The following parts are to O.E.M. only and shall have documentation to prove:
" reman cylinder head " reman cylinder packs " reman engine oil pump " reman engine oil cooler " reman turbo cartridges " reman camshaft " reman jw pump " reman injectors " reman starter and alternator " reman sea water pump " thermostats " main, rod and thrust bearings " hoses and coolant " engine oil and filters " front and rear bearings " gasket kits
Labour
All labour must be completed by Caterpillar factory certified technicians with documentation to prove. This shall include, but is not limited to:
" removing and installing pump and mounting " removing and installing engine components " installing required parts for rebuild " installing all necessary reman components " cleaning and testing required coolers, shut downs and alarms
3. Contractor shall include a $5000 allowance to have Atlantic Caterpillar inspect and verify the proper configuration of the engine ECU. This configuration shall be verified prior to running up the rebuilt engine. This allowance shall be adjusted by 1379 action.
4. Contractor shall be present during initial engine start and seatrials to ensure proper engine operation and to satisfy any FSR warranty requirements. The contractor shall provide 1 year warranty on all parts and labour.
5. Contractor shall provide Vessel's Representative with 3 copies of all work completed and parts used during overhaul.
The final cost for replacement parts, including any unacceptable cores, shall be adjusted by 1379 action upon receipt of final invoicing
Delivery Date: Above-mentioned
The Crown retains the right to negotiate with suppliers on any procurement.
Documents may be submitted in either official language of Canada.
Not stated in the notice: procurement type, procurement method, selection criteria, region of delivery, region of opportunity, expected contract period, end user
No amendments observed.
No attachments listed in the open data.
No contact listed in the open data.