TOITURES PARTIELLES ET PLAFONDS BIBLIOTHÈQUE | Government contract · CanPursue
Contracts
active
TOITURES PARTIELLES ET PLAFONDS BIBLIOTHÈQUE
La Commission scolaire Lester-B.-Pearson
Les Constructions P.R.V. Inc.
2503EG
Watch
Total contract value
$3.4M
Original award value
$2.3M
Start
Mar 31, 2026
End
Jul 31, 2026
Timeline
Official
Awarded
Mar 31, 2026. Original award value: $2.3M
Amendment 1
Sep 29, 2026. ODC06 - Ajustement au contrôle d’éclairage et protection de AC-1
Amendment 2
Jun 30, 2026. URGENCE - Démolition de 2 section de maçonnerie
Amendment 3
Aug 25, 2026. ODC2 (A05)-Démolition 10 sections maçonnerie, suite à l'inspection d'ing
Amendment 4
Aug 25, 2026. ODC3 (A01-S01) - Reconstruction 12 parties de maçonnerie instables
Amendment 5
Aug 25, 2026. ODC4 - Remplacement isolant supplémentaire bassins C-2-I a C-2-IV
Amendment 6
Aug 25, 2026. ODC5 (A04-S02) - Ajout de linteaux sur 3 facades du gymnase arrière
Amendment 7
Sep 29, 2026. ODC07 - Travaux supplémentaires de maçonnerie suite à une inspection en structure et travaux de fissures des parapets
Amendment 8
Oct 15, 2026. ODC09 - Nouveaux conducteurs pour VE-11
Amendment 9
Oct 20, 2026. ODC10- A10_interventions parapet et pente bassin A-IIa
Observed expiry
Jul 31, 2026