Rénovation et agrandissement - 70, rue Saint-Henri, Rivière-du-Loup | Government contract · CanPursue
Contracts
terminated
Rénovation et agrandissement - 70, rue Saint-Henri, Rivière-du-Loup
Société québécoise des infrastructures.
Construction Citadelle Inc.
34011000
Watch
Total contract value
$16.5M
Original award value
$13.6M
Start
Jul 19, 2018
End
May 31, 2023
Timeline
Official
Awarded
Jul 19, 2018. Original award value: $13.6M
Amendment 1
Jan 13, 2021. Modifications significatives Client / Conditions de chantier
Amendment 2
Jul 26, 2021. Modifications significatives Client / Conditions de chantier
Amendment 3
Oct 6, 2021. Modifications significatives Client / Conditions de chantier
Amendment 4
Nov 9, 2021. Modifications significatives Client
Amendment 5
Mar 27, 2023. Modifications mineures et imprévus de chantier
Amendment 6
Apr 21, 2023. Modifications significatives Client
Amendment 7
Dec 17, 2021. Conditions de chantier / Modifications mineures Client
Amendment 8
Sep 10, 2020. Conditions de chantier / Modifications significatives Client
Amendment 9
Mar 2, 2021. Modifications significatives Client
Amendment 10
Apr 19, 2021. Modifications significatives Client / Conditions de chantier
Amendment 11
Mar 2, 2022. Modifications significatives Client / Modifications mineures aux travaux
Amendment 12
Feb 9, 2022. Modifications significatives Client
Amendment 13
Jun 3, 2021. Modifications significatives Client / Conditions de chantier
Amendment 14
Aug 25, 2020. Modifications significatives Client
Amendment 15
Nov 9, 2020. Modifications significatives Client
Observed expiry
May 31, 2023