Pavillon 5 drainage des fondations - Phase II | Government contract · CanPursue
Contracts
active
Pavillon 5 drainage des fondations - Phase II
CÉGEP Sherbrooke
Les Entreprises Richard Brisson Inc
2022-T
Watch
Total contract value
$479.1K
Original award value
$467.7K
Start
Jan 27, 2023
End
May 27, 2023
Timeline
Official
Awarded
Jan 27, 2023. Original award value: $467.7K
Amendment 1
Feb 9, 2024. OC-C-03 AJOUT D'UNE BOITE À CADENAS SUR L'ENCLOS À VÉLOS
Amendment 2
Dec 6, 2023. Ordres de changement OC-C-01, OC-C-02, OC-E-03
Amendment 3
Apr 30, 2024. OC-C-04 RÉALISATION DES TRAVAUX DEMANDÉS DC-C-07, FONDATION PLUS PROFONDE QUE PRÉVUE
Observed expiry
May 27, 2023