RÉAMÉNAGEMENT DE LA SALLE DE SPORTS DU PAVILLON GÉRARD-ARGUIB | Government contract · CanPursue
Contracts
terminated

RÉAMÉNAGEMENT DE LA SALLE DE SPORTS DU PAVILLON GÉRARD-ARGUIB

CÉGEP de Jonquière.LES CONSTRUCTIONS TECT-HAB INCS20 835
Watch
Total contract value
$994.9K
Original award value
$853.5K
Start
Jul 2, 2020
End
Jun 30, 2021

Timeline

Official
  • AwardedJul 2, 2020. Original award value: $853.5K
  • Amendment 1Feb 11, 2021. AJOUT D'UN BOÎTIER DE CONTRÔLE D'ACCÈS - ORDRE DE CHANGEMENT #28
  • Amendment 2Feb 11, 2021. RELOCALISATION INTERRUPTEURS ET PRISE ET AJOUT CIRCUIT - ORDRE DE CHANGEMENT #23, AJOUT CONTRÔLE D'ACCÈS - ORDRE DE CHANGEMENT #24, CÂBLAGE ALARME INCENDIE - ORDRE DE CHANGEMENT # 27
  • Amendment 3Feb 11, 2021. BOÎTE DE SORTIE POUR CONTRÔLE MURAUX - ORDRE DE CHANGEMENT #32
  • Amendment 4Feb 11, 2021. RELOCALISATION DU FILAGE AU PLAFOND - ORDRE DE CHANGEMENT #21
  • Amendment 5Dec 2, 2020. AJOUT RAIL AU PLAFOND ET MISE À NIVEAU DU PLANCHER - ORDRE DE CHANGEMENT #10
  • Amendment 6Apr 16, 2021. AJOUT PRISES POUR BRANCHEMENT RUBAN LED ET PLINTHE - ORDRE DE CHANGEMENT #34
  • Amendment 7Apr 29, 2021. AJOUT DE RAIL AU PLAFOND - ORDRE DE CHANGEMENT #19
  • Amendment 8Dec 2, 2020. ORDRES DE CHANGEMENT #1 À 9
  • Amendment 9Feb 22, 2021. CORRECTION ET DÉTAILS DIVERS - ORDRE DE CHANGEMENT # 26
  • Amendment 10Feb 1, 2021. DIVERS TRAVAUX - ORDRE DE CHANGEMENT #13, AJUSTEMENT HAUTEUR LUMINAIRES - ORDRE DE CHANGEMENT #14, AJOUT GYPSE LOCAL ACCUEIL - ORDRE DE CHANGEMENT #15, AJUSTEMENT MURS PEGBOARD - ORDRE DE CHANGEMENT #17
  • Amendment 11Feb 11, 2021. INSTALLATION D'UN SYSTÈME DE SON - ORDRE DE CHANGEMENT #31
  • Amendment 12Apr 29, 2021. AJOUT DE TIGES FILETÉS POUR FIXATIONS LUMINAIRES - ORDRE DE CHANGEMENT #33
  • Amendment 13Feb 22, 2021. AJOUT QUINCAILLERIE ET BANCS - ORDRE DE CHANGEMENT #18
  • Amendment 14Jan 4, 2021. CHANGEMENT DE MODEL D'ABREUVOIR - ORDRE DE CHANGEMENT # 29
  • Amendment 15Feb 11, 2021. REMPLACEMENT PANNEAU L9-200 - ORDRE DE CHANGEMENT #22
  • Amendment 16Dec 2, 2020. RÉPARATION DE PLANCHER - ORDRE DE CHANGEMENT #11
  • Observed expiryJun 30, 2021
Contract number
S20 835
Awarded
Jul 2, 2020
Instrument
—
Status
terminated
Amendments
16 amendments