Lots 10.20 et 10.32 - Démolition partielle phase 1 (10.20) et phase 2 (10.32) - Agrandissement du Musée d’art contemporain de Montréal au 185, rue Sainte-Catherine Ouest, Montréal (Québec) H2X 3X5 | Government contract · CanPursue
Contracts
active
Lots 10.20 et 10.32 - Démolition partielle phase 1 (10.20) et phase 2 (10.32) - Agrandissement du Musée d’art contemporain de Montréal au 185, rue Sainte-Catherine Ouest, Montréal (Québec) H2X 3X5
SQI - Gestion de projets
DEMOLITION ET EXCAVATION DEMEX INC.
44535083
Watch
Total contract value
$4.7M
Original award value
$3.9M
Start
Dec 15, 2023
End
—
Timeline
Official
Awarded
Dec 15, 2023. Original award value: $3.9M
Amendment 1
Sep 25, 2025. Dépenses suppleméntaires ODC 051 et ODC 079
Amendment 2
Feb 2, 2026. ODC 90 et 91
Amendment 3
Jun 19, 2026. ODC 108 et 109
Amendment 4
Aug 18, 2026. ODC 111
Amendment 5
May 11, 2026. ODC 106
Amendment 6
Apr 6, 2026. ODC 101
Amendment 7
Jul 16, 2026. ODC 110
Amendment 8
Dec 5, 2025. Dépenses suppleméntaires ODC 50, ODC 080 à 087 et ODC 089
Amendment 9
Jun 25, 2025. Dépenses suppleméntaires ODC01, ODC003 À ODC049, ODC052 à 056, ODC058 À ODC78
Amendment 10
Mar 11, 2026. ODC 92 et 97