⌘K
EN
FR
Travaux correctifs d'égouttement pluvial au CLSC de Laurier-station. | Government contract · CanPursue
Contracts
terminated
Travaux correctifs d'égouttement pluvial au CLSC de Laurier-station.
CISSS de Chaudière-Appalaches
Excavation Alex Martineau inc.
2020CNT102
Watch
Total contract value
$25,318.32
Original award value
$24,870.87
Start
Dec 16, 2020
End
Apr 19, 2021
Timeline
Official
Awarded
Dec 16, 2020. Original award value: $24,870.87
Observed expiry
Apr 19, 2021